LITANI C800 PROJECT - CS1 HANDING OVER |
|
On the 1st of July, 2020, the handing over committee nominated by CDR (Council for Development and Reconstruction) along with the following representatives:
-
End User: Litani National River Authority
-
Group of Consultants: Lahmeyer Company, Gauff Company, Dar Al-Handasa Company - Chaer
-
Main Contractor: Mohammed Abdulmohsin Al Kharafi & Sons for General Trading, General Contracting and Industrial Structures W.L.L.,
Electro-Mechanical Subcontractor: Salameh Engineering, Trading & Contracting Co (Setco S.A.L.),
Civil Subcontractor: Ward Company,
have checked all the installations of the first part (CS1) which were implemented to Conveyor 800 project including the following:
-
5 megawatts Mini Hydro Power Plant
-
66 KV Electrical Substation
-
Main building and its offices to operate the project remotely as it will be equipped by Scada System,
-
Yohmor tunnel with 2 access branches:
-
Access Road to Litani River Crossing
-
End of the tunnel consisting of intake structure to contract Section 2 comprising of Shaft & Emergency Gate
The joint team confirmed the proper implementation of this part and its readiness to be Handed Over.
|
|
|
|
|