TAYBEH |
|
PROJECT 2477 |
|
RIVER WORKS |
|
River works consist of the following:
-
construction of 3 box culverts
-
2 settlement channel
-
3 flood evacuators
-
upstream river accessible road
-
River stability
-
Pumping station facilities ,drywells, pipeline collector with complete set of valves telemeasurement equipment, parts and accessories
-
6000 volts control building and office
-
road reinstatement
-
Street lighting poles
-
telemeasurement chamber, guard house
|
|
|
|
|
PUMPING STATION |
|
The Electromechanical Works include but not limited to:
-
6000 Volts Pumping Station of 4 Submersible Pumps of 370m³/h Head of 600m.
-
The Complete Set of Valves, Parts, Accessories, Telemeasuring Equipment and all associated Works.
-
Dry Wells 20 m Deep.
-
6000 Volts Control Panels of 820 KW Solid State Soft Starters.
-
Manifold of Existing and New Transmission Pipeline with Valves and Accessories.
-
Electromechanical Works for Irrigation Pumping Station.
|
|
|
|
|
TRANSMISSION PIPELINE |
|
In addition to the transmission pipe line the following works were done:
AT THE RIVER Settlement channel drain, water inlet pipes and strainers to the wells, well head chambers drain, open ground reservoir drain, etc….
AT HILL SITE the feeding pipeline to the distribution reservoir, all existing and new hydraulic structures drains and water supply to various existing buildings. It includes also the irrigation pipeline.
|
|
|
|
|
ACCESS ROAD |
|
Construction of geogrid walls including:
Asphalting the whole width.
Concrete channel ditches.
Cross drain channel.
Inspection chambers etc ….
|
|
|
|
|
TREATMENT PLANT |
|
Treatment Plant At Hill Site Consist of:
-
Chlorination Building.
-
Ozone Control Room with Ozone Reactor.
-
Treatment Plant of 25000m³/day using Chemical Dosing System, Decanters and Rapid Sand Filters.
-
Quality Control Laboratory.
-
Telemeasuring Equipment.
-
Street Lighting Poles.
-
Stand By Generator 110 KVA for Back Up Facilities.
-
Landscaping and Roads.
-
Boundary Wall.
-
All Associated Civil Works for the 66000 Volts Mobile Substation.
-
Civil Works for 15000-380 Volts Electrical Substation.
-
Irrigation Pumping Station.
|
|
|
|
|
PROJECT 4429 |
|
REHABILITATION OF EXISTING BUILDINGS |
|
Rehabilitation of Existing Buildings include the Full Refurbishment of Civil Works Waterproofing, Electrical Low Current Power and Lighting, Communication, Plumbing, Ventilation, Metal of Aluminum Joinery, Woodwork, Glaziery, Painting, Tiling, Cladding, Clay Tiling, Landscaping, Domestic Wastewater Treatment Plant…etc |
|
|
|
|
POWER SUPPLY |
|
Power Supply includes but not limited to:
-
Supply and Installation of Complete Set of Transformers , Cells and Panels, Cables and all others for Two Electrical Substation of 15000 to 6000 Volts and of 15000 to 380 Volts.
-
15000 Volts Overhead Tension Cables Columns and Connections including Transformers from 15000 Volts to 6000 Volts and from 15000 Volts to 380 Volts.
-
All Electrical Associated Works from 66000 Volts Mobile Substation to Electrical Substation.
|
|
|
|
|
|
|
|
|
|
|